title: Where a run spends its time
---

A pipeline's wall-clock floor is not its total runtime — it is the longest chain
of dependencies, because nothing on that chain can be run in parallel with the
rest of it. `pipeline_profile()` reports both, and `critical_path()` is the walk
underneath.

Two chains, one deliberately slow:

```{r}
#| comment: "#>"
proj <- file.path(tempdir(), "profile-demo")
dir.create(proj, recursive = TRUE, showWarnings = FALSE)

writeLines(c(
  "library(targets)",
  "",
  "list(",
  "  tar_target(seed,   { Sys.sleep(0.2); 1 }),",
  "  tar_target(slow_a, { Sys.sleep(0.6); seed + 1 }),",
  "  tar_target(slow_b, { Sys.sleep(0.6); slow_a + 1 }),",
  "  tar_target(slow_c, { Sys.sleep(0.6); slow_b + 1 }),",
  "  tar_target(quick,  { Sys.sleep(0.1); seed * 10 }),",
  "  tar_target(report, paste(slow_c, quick))",
  ")"
), file.path(proj, "_targets.R"))

withr::with_dir(proj, targets::tar_make(callr_function = NULL))
```

Read the pipeline, then profile it. `check_outdated = FALSE` skips the re-hashing
pass; freshness is not what this example is about.

```{r}
#| comment: "#>"
cfg <- tardoc::build_site_config(proj)
tardoc::setup_site_dirs(cfg)
td <- tardoc::load_targets_data(cfg, check_outdated = FALSE)

prof <- tardoc::pipeline_profile(td)

prof$slowest
```

```{r}
#| comment: "#>"
prof$critical_path

c(total_seconds    = round(prof$total_seconds, 2),
  critical_seconds = round(prof$critical_seconds, 2))
```

The critical path is `seed → slow_a → slow_b → slow_c → report`. Its total is the
floor on a full rebuild however many workers you give `tar_make()`: `quick` can
run alongside the slow chain, so its time is free, and shortening it would save
nothing. That is the number worth optimising, and the viewer draws it on the
graph.

`critical_path()` works on any `{name, seconds}` frame and edge list, so you can
run it against your own weights — estimated cost, memory, anything:

```{r}
#| comment: "#>"
nodes <- data.frame(name = c("a", "b", "c", "d"), seconds = c(1, 10, 1, 1))
edges <- data.frame(from = c("a", "a", "b", "c"), to = c("b", "c", "d", "d"))
tardoc::critical_path(nodes, edges)
```